Rock Button Bits operating procedure

  1. The director of the screw drill should receive corresponding training, fully understand and master the structure, performance and use of the pile driver, be able to operate it proficiently, and hold a certificate.
  2. Before construction, the equipment should be inspected in detail to ensure that the drill pipe and other components are free from damage and deformation; pay attention to the center line of the drill pipe and power head, and the allowable deviation is 1% of the total length. Once the drill pipe over 10m is connected to the ground, it cannot be lifted and installed.
  3. The work site must be pave and compacted to ensure that the drilling rig is placed stably and firmly.
  4. Before operation, press the doorbell or horn to send out a warning signal to remind the construction personnel to leave the scene.
  5. Before starting, the joystick should be placed in the neutral position, and the equipment should be started for an idling test to check whether the instrument, temperature, sound, brake and other indicators are normal, and start the operation after confirming that it is normal.
  6. When drilling, if you find body shaking, displacement or tilt and abnormal sound, you should stop drilling immediately, find out the cause and deal with it in time.
  7. When the drilling rig sends out the limit alarm for tripping and descending, stop drilling and gently lift up the drill rod. After the alarm stops, continue drilling.
  8. During the operation of the drilling rig, the operator should pay close attention to the conditions displayed on the dashboard. In case of abnormal conditions, the operator should stop the drilling rig immediately. If there is a jam or abnormal sound, the machine should also be turned off.
  9. Be sure to check whether the body parts are loose and tighten them in time to prevent accidents.
  10. During operation, equipment maintenance is not allowed and can only be carried out after shutdown. Machines that have not been used for a long time should be sealed after inspection. The motor and other parts should be treated with moisture proof.
  11. When extending drill rods or installing pile caps, Water Well Drilling Tools manipulators and other operators must wear safety helmets, safety belts and other safety protection equipment.